Motorists and cyclists using Richmond Park should expect disruption and delays during the implementation of TfL Cycle Quietway 21 from Ham Gate to Roehampton Gate via Middle Path, Pen Ponds and Sheen Cross.
Our contractors will require traffic light controls and a road closure in order to install the three raised crossings and the cycle route improvements.
Details of disruptions:
- Ham Gate entrance will be closed from March 13 - March 17.
- There will be a two-way light at Ham Cross on the road running from Richmond Gate to Kingston Gate in late March for up to two weeks.
- There will be traffic control/lights at Sheen Cross roundabout in March or early April for up to two weeks.